施工合同履行过程中发包人要求变更工程质量标准及其他实质性变更,应( )。
A.由原设计单位同意
B.由发包人和承包人的协商解决
C.报规划管理部门审批
D.由总监理工程审核批准
答案
参考答案:B
施工合同履行过程中发包人要求变更工程质量标准及其他实质性变更,应( )。
A.由原设计单位同意
B.由发包人和承包人的协商解决
C.报规划管理部门审批
D.由总监理工程审核批准
参考答案:B
从方框中选择恰当的单词或词组填入句中,注意使用其正确形式:(每小题1分,满分10分)(请将答案写在答题纸的相应位置)
小题2:. The sudden ________ of the policeman caused the thief to run away. 小题3:. He has been asked to ________________ his absence. 小题4:. Though he was told it was hard to find a job there, he still decided to ____________. 小题5:. To ___________something such as weight or speed means to have an increase in that particular thing. 小题6:. An ____________ person is very active and does not feel at all tired. 小题7:. Sometimes, ____________ is not necessarily harmful, for example, white lies. 小题8:. The movie reminds of me the small village where I was ________________. 小题9:. He is not poor,_______________, he is a millionaire. 小题10:. The party worked hard and at last they _______________ the support they had lost. |