问题 阅读理解

阅读理解。

     Hello, everyone. Here is something important for everyone going to London next month. As you

know, you are going to stay with a family for two weeks. Now, the most important thing is money.

You should take about $530 with you. I think it will be enough for everyone. Then, when you arrive,

your new family will meet you. You must remember to wear a red shirt, so the family will find you

easily. They've been told you all wear red shirts. You'll also need to take with you 4 photos of yourself

and, of course, it's very important that you take the school letter. While you're there, if you have any

problems, you can call Leech School Office. I'll give you the office phone number now: it's 580-4436

and the person to ask for is Mr. s Belcher…She's in the office from nine o'clock in the morning until

five in the afternoon every day. OK. That's everything. Have a good journey!      

1. Where are they going to?  

     _____________________________________    

2. How long are they going to stay there for ?      

    _____________________________________ 

3. Why must they wear red shirts?

     Because the family_____ them_____.      

4. What's the school office telephone number?      

     _____________________________________  

5. What could Mr. s Belcher’s job be according to the reading?

     She could be a (an) _____.     

答案

1. To London.

2. For two weeks.

3. Because the family will find them easily.

4. 580-4436

5. She could be a teacher/ an officer.

选择题
问答题

(四)
某机电安装工程项目,某建筑公司于2010年3月8日与某建设单位签订了修建建筑面积为3000m2工业厂房(带地下室)的施工合同。该建筑公司编制的施工方案和进度计划已获监理工程师批准。
施工进度计划已经达成一致意见。合同规定由于建设单位责任造成施工窝工时,窝工费用按原人工费、机械台班费60%计算。
在专用条款中明确6级以上(含6级)大风、大雨、大雪、地震等自然灾害按不可抗力因素处理。工程师应在收到索赔报告之日起28天内予以确认,工程师无正当理由不确认时,自索赔报告送达之日起28天后视为索赔已经被确认。
根据双方商定,人工费定额为30元/工日,机械台班费为1000元/台班。
建筑公司在履行施工合同的过程中发生以下事件:
事件1:基坑开挖后发现地下情况和发包商提供的地质资料不符,有古河道,须将河道中的淤泥清除并对地基进行二次处理。为此,业主以书面形式通知施工单位停工10d,窝工费用合计为3000元。
事件2:2010年5月18日发生6级大风,一直到5月21日开始施工,造成20名工人窝工。
事件3:5月21日用30个工日修复因大雨冲坏的永久道路,5月22日恢复正常挖掘工作。
事件4:5月27日因租赁的挖掘机大修,挖掘工作停工2d,造成人员窝工10个工日。
事件5:5月29日,因外部供电故障,使工期延误2d,造成20人窝工,2台施工机械窝工。
事件6:在施工过程中,发现因业主提供的图样存在问题,故停工3d进行设计变更,造成人工窝工的60个工日,机械窝工9个台班。

问题


分别说明事件1至事件6的工期延误和费用增加应由谁承担。并说明理由。如是建设单位的责任应向承包单位补偿工期和费用分别为多少?