问题
单项选择题
If the L/C stipulates“the latest shipping date is June 20,2009”,which of the following actual shipment date is wrong( )
A.June 15,2009
B.June 18,2009
C.June 20,2009
D.June 21,2009
答案
参考答案:D
解析: the latest shipping date意为最迟装运日,卖方必须在最迟装运日当天或之前把货物装上运输工具或者交给承运人。