问题 单项选择题

The responsibility assignment matrix(RAM) ______ .

A.is used for development of the project budget

B.is developed at the activity level and used to closely link project roles and responsibilities to project network activities

C.is used to show the connections between work that needs to be done and project team member It can show responsibilities at various levels of detail

D.is used to identify accountabilities in individual performance appraisals

答案

参考答案:C

解析: 职责分配矩阵(RAM) ______ 。 A) 用来计算项目预算 B) 在活动层次开发. 用来联系项目角色和责任到项目网络活动上 C) 用来显示需要做的工作和项目团队成员之间的联系,可以在不同的详细程度上显示责任 D) 用来识别在个人绩效评估上的责任 责任矩阵(RAM)显示出项目成员在每个活动中的责任,RAM可以在不同层次上显示工作与团队成员的关系。