问题 单项选择题

As part of monitoring and controlling, project performance must be monitored and measured regularly to identify variances from the plan. All the following are processes involved with controlling EXCEPT______.

A.verify scope

B.risk monitoring and control

C.performance reporting

D.quality assurance

答案

参考答案:D

解析: 作为监视和控制的一部分, 必须根据计划对项目绩效进行有规律的监视和测量。 下列所有都属于控制过程, 除了______。 A) 核实范围 B) 风险监视与控制 C) 绩效报告 D) 质量保证 质量保证属于执行过程组。