问题 完形填空
完形填空。
     Mr. and Mrs. Jones don't often go out    1   , but last Saturday, Mrs. Jones    2    to her husband, "There is
a good    3    tonight. Can we go and watch it?"
     Mr. Jones was quite    4    about it, so they went and    5    of them liked the movie very much.
     They came out of the cinema at 11 o'clock pm, got into their     6   and began to drive home. It was quite
dark, then Mrs. Jones said to Mr. Jones, "Look! A woman is running along the road very    7    , and a man is
running after her. Can you see them?"
     Mr. Jones said, "Yes, I can." He drove the car slowly near the woman and said to her, "Can we    8    you?"
"No, thank you," the woman said, but she didn't stop     9   . "My husband and I always run home after the
movie, and the    10    one does the cleaning at home."
(     )1. A. in the morning
(     )2. A. told          
(     )3. A. movie         
(     )4. A. angry         
(     )5. A. both           
(     )6. A. seats         
(     )7. A. fast          
(     )8. A. leave          
(     )9. A. to run        
(     )10. A. last          
B. in the evening 
B. talked        
B. match        
B. afraid        
B. all                       
B. chairs         
B. slowly        
B. notice         
B. running         
B. angry      
C. in the afternoon 
C. spoke            
C. meeting           
C. worried            
C. every           
C. car              
C. late             
C. help            
C. runs               
C. happy        
D. at noon   
D. said     
D. message  
D. happy    
D. no        
D. train    
D. long      
D. love    
D. ran      
D. great 
答案

1-5  BDADA  6-10  CACBA

问答题 案例分析题

背景

某六层砖混结构的住宅楼,基础为钢筋混凝土条形基础,委托A理公司监理,经过招标投标,B建筑工程有限公司中标,并成立了项目部组织施工。该工程2008年3月8日开工,2009年1月28日工程整体竣工,并交付使用。施工过程中发生如下事件:

事件一:主体工程施工完成后,建设单位编制了《主体验收工作预案》。其中针对工程实体准备内容规定:墙面上的施工孔洞按规定镶堵密实,并作隐蔽工程验收记录;混凝土结构工程模板拆除并对其表面清理干净,混凝土结构存在缺陷处整改完成;楼层标高控制线清楚弹出墨线,并做醒目标志;工程技术资料存在的问题悉数整改完成。监理工程师认为内容不全。

事件二:主体工程施工完成后,建设单位编制了《主体验收工作预案》。其中针对T程资料准备内容规定:施工单位在主体工程完工之后对工程进行自检,确认工程质量符合有关法律、法规和工程建设强制性标准提供主体结构施工质量自评报告,该报告应由项目经理和施T单位负责人审核、签字、盖章;监理单位在主体结构工程完-二后对工程全过程监理情况进行质量评价,提供主体工程质量评估报告,该报告应当由总监和监理单位有关负责人审核、签字、盖章;勘察、设计单位对勘察、设计文件及设计变更进行检查对工程主体实体是否与设计图纸及变更一致,进行认可;有完整的主体结构工程档案资料、见证试验档案、监理资料;施工质量保证资料;管理资料和评定资料。监理工程师认为内容

不全。

事件三:主体工程施工完成后,建设单位编制了《主体验收工作预案》。其中针对组织及程序内容规定:由建设单位负责组织主体验收小组;验收组成员由建设单位负责人、项目现场管理人员组成;建设工程主体验收按施工企业自评、设计认可的程序进行。监理工程师认为不妥。

事件四:室内防水工程施工前,项目部编制了《防水工程施工方案》。其中规定质量验收的文件和记录有:设计图纸及会审记录、设计变更通知单和材料代用核定单;施工方法、技术措施、质量保证措施;施工操作要求及注意事项。监理工程师认为不妥。

问题

(1)事件一中,主体结构验收工程实体准备还应包括哪些内容?

(2)事件二中,主体结构验收工程资料准备还应包括哪些内容?

(3)事件三中,主体结构验收人员还应包括哪些内容?

(4)事件三中,主体结构验收程序还应包括哪些内容?

(5)事件四中,室内防水工程施工质量验收的文件和记录还应包括哪些内容?

问答题 简答题