问题
单项选择题
()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.
A、gantt chart
B、project histogram
C、milestone chart
D、project flowchart
答案
参考答案:A
解析: