问题 问答题


某施工总承包单位于2005年5月与某公司签订了框架一剪力墙办公楼工程的施工合同。该工程建筑面积28350m2,地上22层,地下2层。施工单位编制的施工组织设计和进度计划已获得监理工程师批准。2005年6月24日,工程正式开工,地下连续墙工程由分包商进行施工。在实际施工过程中发生了以下事件。
事件1:在开挖过程中,遇到砂土层,监理工程师6月30日下停工令,其后进行地质复查;7月4日接地监理工程师下达复工令,要求7月5日复工。
事件2:因分包商施工的地下连续墙出现质量问题,拖延工期5日,影响了施工的正常进行。
事件3:7月25日~28日,由于当地出现罕见暴雨迫使工程暂停,造成人工窝工20个工作日。
(注:以上事件均发生在关键线路上)
[问题]

由于工程施工地质条件的变化造成的工期拖延,施工总承包单位向业主提出的工期索赔是否成立请说明原因。

答案

参考答案:

解析:施工总承包单位向业主提出的工期索赔成立。 理由:地质条件原因造成工期拖延的责任在于建设单位(不是承包单位的原因造成的;根据监理工程下达的停工令停工),所以该项事件的工期索赔成立。

阅读理解

Six Americans are working on a new highway. But this highway won't have any traffic.It's an "ice highway" to the South Pole.

The team has just finished a second year of work on the 1,020-mile highway. "The road is the greatest single footprint of activity we've seen in the Antarctic (南极洲)," said Alan Hemmings, an Australian environmentalist.

The highway will provide a new way for supplies to be trekked (拉, 搬) across the earth on tractor-pulled sleds (雪橇). This method will use a lot less fuel than an aircraft, the current (当前的) way that scientists and supplies reach the Amundsen-Scott Base, a U.S. research station in the South Pole. The highway will also allow for equipment that is too big for planes to carry to be brought to Antarctica.Even with these benefits, there is one disadvantage—a round trip on the road will be 30 days, compared to a few hours by plane.

Making this 20-foot-wide road isn't easy, and it takes a lot of time. The crew (工作队) has been working on the road for two summers, when it's warmer and easier to work with the ice. It probably won't be completed until 2006.

Crevasses (裂缝), or cracks, in the land often make the construction difficult. Crevasses are kind of like pot holes that form when surface ice is stretched.This can be very dangerous, especially when the crevasses are hidden under a layer (层) of snow and can't be seen.

"Last year it took us three months to go three miles across a crevasse field, full of dangerous, hidden crevasses," said the project's manager, John Wright. Each year, more crevasses appear and they have to be filled with snow and ice so the road is safe for travel. The road will also be lined with green flags so travelers know where the safe surface is.

小题1: It will probably take ______ years to complete the ice highway.

A.2

B.4

C.6

D.8小题2:When it is finished, the highway will not be used for ______.

A.giving supplies to the research station in the South Pole

B.taking scientists to the South Pole

C.taking travelers to a tour of Antarctic

D.bringing huge equipment to Antarctic小题3:How many miles can be covered at most each day if you take the ice highway to the South

Pole?

A.30.

B.34.

C.68.

D.88.小题4:Which of the following is true according to the passage?

A.Other crevasses won’t appear if a crevasse has been filled.

B.Many new crevasses will form after a crevasse has been filled.

C.Travelers can drive their sleds on the ice highway freely.

D.There will be less danger if the crevasses are covered by snow.

单项选择题